February 14th, 2010
Just wanted to update everyone on two topics.
First, if you’re following the solar graphs for the Coop, you might notice that some days there is zero solar energy generated. This is because the new inverter we installed “buzzes” quite a bit more then the older inverter. The buzzing only happens when its cloudy, but its very annoying and the staff have been turning it off on cloudy days. It should get better once we get more sunny days this spring. We are also making plans to move the inverter outside.
Second, City Hall is still not turned on. DTE came the other day to install the meters and commission the system, but there was a mix-up and they brought the wrong type of meter and it wouldn’t fit the in the meter enclosure we provided. We’re working on straightening it out.
Posted in Solar | 1 Comment »
January 11th, 2010
I’ve uploaded new pictures of the 12 panels on the Ypsi Food Coop’s new white roof. There are also new pictures of the bakery’s new white roof and a prototype solar panel rack. Once the weather gets a little warmer we can start installing the 30 panels on the bakery.
Posted in Solar | No Comments »
January 4th, 2010
I’ve added a few more pictures to the City Hall site. The system is fully installed, inspected and tested. I need one more piece of paper signed by the City lawyer, then we can go into full production. Then another week or so for us to finish installing testing the monitoring system.
I’ve also added links to the City Hall rack design drawings. I hope they help with other projects.
Lastly, I’ve update the grant progress reports for both the City Hall and Bakery projects.
Thanks for your support. – Strenski
Posted in Solar | 1 Comment »
November 13th, 2009
The panels are up! Go to SolarYpsi.org/index.php?siteDetails=cityhall to see all the pictures of the installation. Next step is to get the electrician over to City Hall to wire the power into the building’s electrical system. Should happen next week. Then a couple of inspections and a new DTE meter and we’ll be in business. The monitoring software will follow in a week or so after that.
Tags: City Hall
Posted in Solar | No Comments »
October 19th, 2009
The Ypsilanti Food Coop is getting a new roof today and the roofers needed to get under the solar panels, so around noon we turned them off and took the rack apart. The roofers worked quickly and we were able to put the rack back together and turn the panels back on around 6:00pm.
The old roof was black and the new roof is white. This should boost our production of solar power with more reflective light hitting the panels.
Posted in Solar | 2 Comments »
October 6th, 2009
We had hoped to install the solar panels on the back of City Hall yesterday, but did not have enough time to finish.
Here’s a short summary yesterday’s work. Initially we had hoped to raise the frame for the solar panels in one piece. We could easily lift it, but the frame was too flexible, so we disconnected the frame into 3 pieces and raised the center frame. The lift we rent worked great, but it only gives us access to about 1/3 of the wall at a time. We temporary pinned the frame to the wall with some mechanical anchors, while trying to get the frame level and plumb. This proved difficult from the lift. We had to use ropes from the roof to raise and lower the frame, to tweak it into the correct location.
With a couple of mechanical anchors and ropes holding the center section of the frame in place, we drilled the holes for the Hilti HY Max 150 epoxy anchors. These too proved to take longer then expected working from the lift. We drilled, brushed, and blew-out a dozen holes and epoxied in a bunch of anchors. Then we repeat for another bunch of anchors. The epoxy sets up in 1 hour so after lunch we were able to torque down these anchors. We had a few that did not hold, so we had to clean the holes and re-epoxy the anchor.
The metal that is up there is well anchored to the wall. The volunteer crew, is back to work on their normal jobs and we returned the lift. I’m going to talk with the crew later this week, and schedule another day to hopefully finish hanging the panels.
Tim Neff, the electrician for the project, stopped by yesterday to look at his part of the job again. He also pulled the electrical permit for the project. He too is busy, but said he would like to start in a couple of weeks. He’ll need to run conduit from the back wall, through the boiler room, to the electrical room. He’ll also need to run conduit from the electrical room out to the utility meter on the back wall.
Posted in Solar | 1 Comment »
September 11th, 2009
For those of you who know we are planning at some point to launch a JK MicroSystems picoFlash single board computer at the Ypsilanti Food Cooperative to do the data collecting, we wanted to let you know we have completed the housing for the card. The programming of the card is nearing completion as well and we hope to have the whole unit mounted and collecting data soon.
Here is a picture of what the housing looks like.

JK microsystems picoFlash Single Board Computer Housing
Posted in Project Code, Solar | No Comments »
August 19th, 2009
A code update happened this morning and the changes were put into the SourceForge subversion repository (revision #6). The consumption chart was modified to better show actual consumption and a couple of bugs were fixed.
Posted in Project Code | No Comments »
August 19th, 2009
We have gone and done it again. There is now another chart you’ll need to learn to interpret. This one is a consumption chart that show where the electricity used is coming from. To view this chart, bring up the Daily Chart for a live location and click the ‘Show Consumption’ checkbox. The chart will change within a few seconds to the consumption chart.
For those interested in the code behind this wonderful advancement, it has been submitted to the subversion repository hosted by Sourceforge for the SolarYpsi project. Please, go to the project page (here) and rate us thumbs up! It will make us feel better.
Posted in Project Code | 1 Comment »
July 9th, 2009
Yesterday, June 8, HDL (the host of SolarYpsi’s website) experienced problems that are believed to be related to the recent Denial of Service attacks launched against various websites, including some of the United States government. They worked quickly to get us back online and we want to thank them for their effort.
Unfortunately, there are significant gaps in the data from June 8. The SolarYpsi development team is working on a solution to help prevent the loss of data in the future if this should happen again.
Posted in Project Code, Solar | 1 Comment »