City Hall Solar Project – Update

The panels are up! Go to SolarYpsi.org/index.php?siteDetails=cityhall to see all the pictures of the installation. Next step is to get the electrician over to City Hall to wire the power into the building’s electrical system. Should happen next week. Then a couple of inspections and a new DTE meter and we’ll be in business. The monitoring software will follow in a week or so after that.